The quote for a light steel building is often prepared in a separate spreadsheet: member weight, cladding area, consumables and interior finishes are counted by hand. As the design changes, the spreadsheet goes out of date and a gap opens between the quote and the building that is produced. Taking quantities from the model closes that gap. This article explains what is counted, why factory and site quantities should be kept apart, and how the quote is prepared from the same numbers.
What is counted?
- Steel members: every member of the framing, with section and length.
- Cladding: the layers fitted to the panel in the factory (plasterboard, OSB, insulation, outer board) and trapezoidal sheets.
- Consumables: screws, joint profiles and the like, panel by panel.
- Room finishes: floor, wall and ceiling finishes (plaster, paint, tiles, screed, parquet…).
- Doors and windows: with their types.
Factory and site are counted apart
Panel cladding and room finishes are separate jobs. The layers fitted to the panel in the factory are the panel's cladding and are counted on the panel; the plaster, primer, paint, tiles, screed and parquet applied on site are the finishes of the rooms and are listed by room number. Mixing the two leads to counting the same material twice, or not at all. In AXIONBIM rooms are listed with level-prefixed numbers (Z-01, 1-01).
Net quantity and purchase quantity
The net quantity from the model is not the quantity to buy: waste is added and the quantity is rounded up to the package size. If the material list shows these two numbers separately, you know both what the building actually contains and what to order. In AXIONBIM the material list opens with Net Quantities and Purchasing tabs and can be exported to Excel or CSV. Material cards are shared by all projects; you define them once.
Preparing the quote from the same numbers
- Enter the prices of the material cards in the price list, or import them from an Excel / CSV file.
- Create a new quote; it is built from that day's material list.
- Enter the customer, currency, exchange rates, VAT, overhead and profit percentages; add extra lines if needed.
- Export the quote PDF to send to the customer.
A quote keeps the prices of the day it was created. When the architectural plan or the framing changes, the quantities and the material list update, and you build a new quote with current prices. That way the number given to the customer and the building that is produced come from the same model.
Depending on your plan
In AXIONBIM, quantities and quotes are modules that depend on your plan; which plans include them is shown on the Pricing page. Step-by-step instructions are in the guide: Quantities and Material Lists, Rooms, Quotes.
Published:
Try it on your own project
Create an AXIONBIM account, download the program and try it free for 7 days from your first login. No card details required.
Other articles
- Light gauge steel house vs container home: how they compare
- Light gauge steel fire resistance: how steel stud walls get rated
- Light Steel Framing Design Methods and Software in 2026
- Light gauge steel construction process: 10 stages explained
- Soundproofing steel stud walls: layers, decoupling and sealing
- Light gauge steel vs structural steel: key differences explained
- All articles