Guide topics

30

Quantities and Material Lists

The QUANTITIES tab counts the material of the project: room finishes (paint, tiles, parquet…), doors and windows, steel profiles, cladding boards and consumables. All of it is collected in a single purchase list; waste is added and quantities are rounded up to packages.

For drawing rooms and room properties see the "Rooms" topic; for prices and quotes see the "Quotes" topic.

Step by step

  1. Define the materials you buy with QUANTITIES › Materials › Material Cards. The cards are shared by all projects; you do it once.
  2. Set up the finish types (floor, wall, ceiling, skirting, roof, exterior facade, ceiling insulation) with QUANTITIES › Types › Finish Types, and the joinery types with Door/Window Types.
  3. Draw the rooms and choose types in the Finishes section of the room properties. Give types to doors and windows with QUANTITIES › Types › Assign Type.
  4. Open the lists with the QUANTITIES › Lists buttons. Assign the roof, exterior facade and ceiling insulation types from their own tabs of the Quantities window.
  5. In the window that Material List opens, see what the project contains on the Net Quantities tab and the quantities to purchase on the Purchasing tab, and take them to Excel with Export to Excel / CSV.

Material cards

QUANTITIES › Materials › Material Cards, Finish Types and Door/Window Types open the same Quantity Library window on the relevant tab. The library is stored in your user folder, is shared by all projects and is not lost when the program is updated. On first opening it comes with sample materials (primer, paint, satin plaster, ceramic, parquet, skirting…); correct the values for your own products. Changes become permanent with Save; if you close without saving, the program asks.

A material card describes how a material is measured and purchased:

  • Code: a unique short name. Lists and prices find the card by this code; the same code cannot be on two cards.
  • Material and Group: the name and group of the card.
  • Type: in which selection lists the card comes first (see "Card type" below).
  • Quantity unit: the unit in which the material is measured: m², m, m³, pcs or kg.
  • Purchase unit: the unit the seller sells in (for example L).
  • Consumption / unit: how many purchase units go into one quantity unit (0.10 L/m² for one coat of interior wall paint).
  • Waste %: the allowance for cutting and loss.
  • Package and Package size: the name of the package and the amount in it (bucket, 15). If the package size is empty, the material is sold without a package.
  • Section hatch: the pattern of this material in the section sheet.
  • Delivered to: where the supplier brings the material: Factory (default) or Site. It shows as a column of the Purchasing list; it is the delivery address when you place the order.
  • Screw length (mm) and Thread pitch (mm): on screw cards, the product's length and thread pitch (e.g. 19 and 1.6 for a 4.8×19 screw). Leave them empty on other cards.
  • Source: whether the card came from the SAP list (see "Importing cards from the SAP list" below).
  • + Add Material adds a new card, Copy adds a copy of the selected card.
  • You can select several rows one by one with Ctrl, or as a range with Shift; filter with Search and select all visible rows with Ctrl+A. Delete Selected deletes all selected rows with a single question.
  • In numbers both comma and dot can be used: in the Turkish interface "2.450" is two thousand four hundred fifty, and "2450,50" and "2450.50" are decimal. If a cell cannot be read, it says which row and column it is and nothing is saved.

Quick search. In the Search box above the table, type words that occur in the code, the name or the group (for example galv 1,2 rulo). The table filters as you type and on the right it says how many rows are visible. You can type several words; order, upper/lower case, Turkish letters and the "1,2" / "1.2" difference do not matter. The filter is only a view; Save writes all cards.

Filters. The filters below the search box narrow a long list and work together with the search box; the number on the right says how many cards are visible.

  • Group: shows the cards by group. In the list the number of cards is written next to each group. A parent group (for example PF1) includes all the groups under it, a subgroup (for example PF1.301) only itself.
  • Kind: only the cards of the chosen kind (see "Card type" below).
  • Source: the cards that came from SAP, the ones you entered by hand, or the ones that are no longer in the last SAP list ("Not in SAP").
  • Only this project's cards: the cards in the material set of the open project (see "Project material set" below): those that occur in the project's material list (steel coil, screw, board, consumable, foundation connection, finish type and door/window type cards) and those added to the set by hand. On the first tick the project is computed once; in a large project this can take a second or two. The used cards are computed from the saved library; a card code you have just changed in the window appears after Save.
  • Only priced: the cards with a price or a labour price. This box appears only when the window is opened from QUOTES › Prices › Price List.
  • Clear Filters empties the search box and all the filters.

Change Kind. This button changes the kind of the cards selected in the table in one go. To give the same kind to all the cards of a group, choose the group, click in the table and press Ctrl+A, then choose the kind from Change Kind; the program asks how many cards will change. The change becomes permanent with Save. When you import the SAP list again, the kind you gave is kept; new cards added to that group later need their kind to be given separately.

Card type. The drop-down lists in which you choose a material card bring forward only the cards of the relevant type, so unrelated cards do not get in the way. The types are: Fastener, Sealing tape / gasket, Sheet and board, Finish material, Door / window and General.

  • The Fastener product list of a panel shows Fastener cards, and the Sill sealer list shows Sealing tape / gasket cards.
  • The layers of a finish type show Finish material, Sheet and board and Sealing tape / gasket cards; the Material card cell of a door/window type shows Door / window cards.
  • Cards of type General, entered by hand, appear in every list. A card that does not appear in a list is also found by typing it in the box; so every card can be chosen from every list. A card chosen earlier stays in place whatever its type.

Searching by typing in a drop-down list. In the drop-down lists where a material is chosen you can type directly in the box (for example asma 60); the list filters as you type with the same rule. Choose by clicking in the list, with the arrow keys or with Enter; when no item is highlighted, Enter chooses the first of the filtered list. Esc or clicking elsewhere without choosing restores the previous choice.

Material picker (… button). The … button next to the places where a card is chosen opens the same picker window: Fastener product and Sill sealer in the panel Properties, the product cells of the foundation connection types, Pick coil… in the sections, and the material cell of finish type layers and of door/window types in the Quantity Library.

  • The three options at the top of the window set which cards are listed: In this project, This kind (Coils in the coil picker) and Whole library.
  • In this project is the material set of the open project (see "Project material set" below): the cards in the material list and those added to the set by hand; the cards of the picker's kind come first. The list is computed once when the window opens; in a large project this can take a second or two.
  • This kind are the cards offered by the "Card type" rule above; Whole library is all the cards.
  • The window opens with the cards of the project; if the project has none, it opens with the cards of the kind. The number next to each option shows how many cards in that scope match the search you type; if the card you are looking for is not in the chosen scope, a note at the bottom of the window says so.
  • The chosen code is written into the box or the cell; in the panel settings the change becomes permanent with Apply, in the library with Save.

Project material set. Every project has its own short material list; the pickers' In this project list and the Only this project's cards filter of Material Cards show it. In a long SAP list you choose the few cards the project needs once and then always work with them.

  • The set has two parts: the cards in the project's material list are in the set automatically; in addition you add by hand the cards you know the project will need. Only the cards added by hand are written to the project file.
  • When you choose a card from Whole library in a picker, the card enters the project's set automatically; next time it appears in the In this project list.
  • In QUANTITIES › Materials › Material Cards select cards and press Add to Project Set or Remove from Set. The project changes at once; Undo reverts it. A card the project uses stays in the set while it is used.

Template sets. If similar projects use the same cards, you can save the set of one project as a named template and use it in another project. Templates are in the library and shared by all projects.

  • Material Cards › Templates ▾ › Save the project's set as a template… makes a template of all the cards of the set (used and added by hand) under a name, e.g. "Container set". If a template with the same name exists, the program asks.
  • Templates ▾ › Add a template to this project's set adds the cards of the template to the open project's set; the project changes at once.
  • Templates ▾ › Delete a template deletes the template. Saving and deleting templates becomes permanent with Save, like the other library changes.
  • A SAP card used in a template is not deleted when you take the SAP list again with Remove SAP cards of the groups not chosen from the library ticked.

Importing cards from the SAP list

If your material records are defined in SAP, you do not need to enter the cards by hand.

  1. In SAP, export the MM60 list with the columns Material, Material short text, Material group and BUoM to Excel or a text file.
  2. On the Material Cards tab, click Import from SAP list… and choose the file.
  3. In the SAP material list window, type the material groups that will become cards, separated by ;; * at the end means a prefix. The recommended value is PF1.*; PF2.* (sheet, board and fasteners). While you type, the window shows how many cards will be added, updated and are not in the SAP list.
  4. Click Import, then Save in the library window.
  • The code of a card is the SAP material number; its name and group are the short text and material group in SAP. The unit comes from BUoM (KG → kg, M → m, M2 → m², ADT → pcs).
  • When you import the list again, the name and group are refreshed from SAP; waste, package, VAT, hatch, note and price are kept. The unit of an existing card is not changed.
  • While the box Remove SAP cards of the groups not chosen from the library is ticked, SAP cards imported earlier from other groups are removed. A card used in a price, a finish type or a door/window type stays; cards you entered by hand are not touched.
  • A card that is no longer in the SAP list is not deleted; the Source column says "Not in SAP".
  • The type of a card that comes from SAP is assigned from the material group; if you change the type yourself, the next import does not change it.

Finish types

QUANTITIES › Types › Finish Types opens the Finish Types tab of the library. A finish type is the finishing layers applied to a surface on site. Each type has a Surface; the code takes a prefix according to the surface:

  • Floor (ZM, for example ceramic, adhesive, waterproofing): multiplied by the floor area of the room.
  • Wall (DV, for example satin plaster, primer, paint): multiplied by the net wall area of the room.
  • Ceiling (TV): multiplied by the ceiling area of the room.
  • Skirting (SP): multiplied by the skirting length (m) of the room.
  • Roof (CT), Exterior facade (DC) and Ceiling insulation (TY): below.

Editing a type:

  • Manage the types with + Add Type, Copy and Delete Selected. Enter the layers of the selected type in the Layers (from the visible face inwards) table below: + Add adds a layer, Delete removes it; ▲ Up and ▼ Down change the order.
  • Coats: how many coats of the same material are applied (two coats of paint = 2). Thickness (mm) is for the section drawing; leave it empty for a thin layer such as paint.
  • The material of a layer must be measured in the unit of the surface: m² for floor, wall and ceiling, m for skirting. If it does not match, nothing is saved and it says which material in which type.
  • Lower zone on a wall (tiles): if the Lower-zone layers are filled in, the wall counts as two zones: the lower zone from the floor up to the Tile height (mm) (tiles, adhesive, waterproofing), and above it the main layers (primer, paint). If the height is empty, it is 2100 mm. It can also be changed per room; for tiles up to the ceiling, type the room height.
  • Skirting parts: in the section table below a skirting type, choose Inner corner piece (pcs), Outer corner piece (pcs) or End piece (pcs) in the Part column and give a card measured in pieces. The program counts these parts in each room from the corners and doors.
  • Panel cladding (plasterboard, OSB, insulation) is not written into a finish type; it is counted on the panel.

Assigning to a room: select the room; in the Finishes section of its properties choose the Floor, Wall, Ceiling and Skirting types, type the tile height if needed and click Apply. A type deleted from the library appears in the room as "(not in library)" and a warning appears; when the type is added back to the library it is found again.

Roof, exterior facade and ceiling insulation types are assigned not to a room but from their own tabs of the Quantities window:

  • Roof type: the upper layers are the covering (tiles, membrane, OSB…) and are multiplied by the sloped area of the roof. In the Edge, soffit and downpipe materials table below, a Part is chosen for each row: Soffit (m²), Eaves / gutter (m), Gable edge (m), Ridge (m), Hip (m), Valley (m), Step / abutment (m) or Downpipe (pcs). Per measure can be pieces per metre (ridge tile 3/m) or pieces per downpipe point (2 elbows); the quantity unit of the material must be the same as the unit of the part. Downpipe spacing (m): number of downpipes = eaves length ÷ spacing, rounded up; if empty, no downpipe is counted.
  • Facade type: the facade work done on site (insulation system, plaster, paint…). The layers are multiplied by the net area of the facade (door and window openings deducted). In the Corner, base, sill, reveal and head materials table below, the parts are Outside corner (m), Base / starter (m), Window sill (m), Reveal: sides + head (m) and Head / drip (m); all are in metres and the unit of the material must be m.
  • Ceiling insulation type: the insulation laid over the ceiling (glass wool, rock wool, vapour balancer…). The layers are multiplied by the insulated ceiling area; for two coats of 5 cm glass wool the coat count is 2.

Door/window types and Assign Type

QUANTITIES › Types › Door/Window Types opens the Door/Window Types tab of the library. Each type has a Code (K-01 for a door, P-01 for a window), a Name, a Type, and a nominal Width (mm) and Height (mm).

  • Sill (mm): windows only; the height of the lower edge of the window above the bottom of the panel (900 mm if empty). PANEL › Doors / Windows › Place Window cuts the window at this height.
  • Material card: if you choose a card whose quantity unit is pieces, the type is counted in pieces in the Material List and can be priced; if empty, the type appears only in the Door/Window Schedule.

To assign a type:

  1. Select the panel where the door or window is in the model (or select the opening row in the model tree) and click QUANTITIES › Types › Assign Type.
  2. In the Assign Door/Window Type window, if there are several doors/windows on the panel, choose one from the Opening box (untyped ones come first).
  3. Choose the type from the Type list. The program suggests the type that fits the size of the opening automatically; (untyped) removes the type.
  4. Tick Only this opening or the option for all openings of the same kind and size (±5 mm) in the project, and click Apply.
  • If you click Assign Type while no panel or opening is selected, the program matches the untyped doors and windows with the types in the library by size (±5 mm), shows the result as a count (for example "K-01 × 12, P-01 × 8") and, if you confirm, assigns all of them at once.
  • The assignment is undone with Ctrl+Z; the size and the frame of the opening do not change.

Lists and the Quantities window

There are four buttons in the QUANTITIES › Lists group. Model Quantities opens a separate window. Room Schedule, Door/Window Schedule and Material List open the same Quantities window on the relevant tab. Material List opens the window on the Net Quantities tab; the Purchasing tab is right next to it.

The tabs of the Quantities window come with the main lists first: Net Quantities and Purchasing (with Quotes next to them when opened from QUOTES); then the breakdowns: Room Schedule, Door/Window Schedule, Finish Quantities, Roof and eaves, Exterior facade and Ceiling insulation.

The columns of the tables widen to fit their text. A long material name, source, room list or panel list wraps to the next line after a certain width; a table that does not fit the window gets a horizontal scroll bar at the bottom. In the warning list at the top of the window, a long line also wraps.

The material list answers three questions: Net Quantities shows what the project contains, Purchasing what to buy, and QUOTES (see "Quotes") what to sell it for. All three come from the same calculation; the common basis is the material card. The room, roof, facade, ceiling, finish and door/window tabs are breakdowns that show where these quantities come from.

  • The window can stay open; after you change the model, click Refresh.
  • The yellow bar at the top shows the number of quantity warnings; clicking it opens the warning list.
  • The price and amount columns and the Quotes tab are visible only in the Quantities and Quotes window opened with QUOTES › Quote › Quotes. There are no prices in the window opened from QUANTITIES; if your package does not have the QUOTES module, price columns are not shown anywhere.

Model Quantities

QUANTITIES › Lists › Model Quantities opens the Structural Member Schedule window. The elements in the model are listed with category, type, description/section, mark, material, phase, count, length, weight, panel gross area, solid surface area and volume. Elements with the same category, type, section, material and phase are collected in one row. If a steel grade is entered for a part, it is written next to the material in the Material column (e.g. "Galvanised sheet · S250GD"); parts with different grades are in separate rows. The Assembly column shows the name of the assembly of the part (e.g. MT-1); the parts of an assembly are collected in a separate row per assembly. The weight of plate and sheet solids is calculated from the volume (7850 kg/m³) and appears in the Weight (kg) column. In the CSV file Assembly is the last column.

  • When you choose one in the Category list at the top, only those rows are shown; for example, when you choose Profile, the window becomes a profile list. The summary below and Export Excel / CSV... use the visible rows.
  • Double-clicking a row or Select in Scene selects the elements of that row in the model and closes the window.
  • The Length of a profile is its machine cut length: cutting allowances and ear extensions are included, and the assembly gap of the active machine's profile recipe is subtracted. It is the same as the panel sheet, the production work order, the machine file and Net Quantities. A profile that does not belong to a panel has no gap subtracted; if there is no active machine, or its recipe does not fit the section, the production length is shown.
  • Weight (kg) is calculated for cold-formed profiles (C, U, Z, Sigma, Omega, flat strap) from the cut length and the weight per metre; if a strip width is entered for the section, that is used. The weight of catalogue sections such as IPE is not known, so their row stays empty and the summary says so separately. In a mesh row the weight is that of the placed wires; Stock m² and Stock kg are for the full sheets.
  • In a panel row, Panel net area is the gross area minus door, window and service openings. The volume of a panel is not written; volume is only given for solids (concrete, solid elements).
  • This window counts the elements in the model. The complete list to purchase, including cladding boards, screws and consumables, is in the Material List; the length-by-length cut list is in the Output Centre.

Room Schedule

QUANTITIES › Lists › Room Schedule gives, for each room, the height, floor area, perimeter, wall gross, openings, reveals and wall net area, the lower and upper zone separately on a tiled wall, the ceiling area, the skirting length, the open edge, railing and parapet lengths and the assigned types. The totals are written at the bottom.

  • A yellow row shows that there is a quantity warning in that room (see the warning list above).
  • Double-clicking a row selects the room in the model. If you select several rows with Ctrl or Shift and double-click, all are selected and can be edited together.

Calculation rules:

  • Floor and ceiling = room area. Wall gross = length of the edges counted as wall × room height (+ parapet length × parapet height).
  • If an edge of the room sits on a wall panel (parallel and within half the panel thickness + 150 mm), all doors and windows of that panel that fall within the room height are deducted as openings. It does not matter whether you draw the room from the wall axis or from the inner face. The door of a wall between two rooms is deducted from both rooms.
  • Reveal inner faces are added: opening perimeter × wall thickness (cladding included). The lower edge of a door and the upper edge of an opening that goes up to the ceiling are not counted. For a wall between two rooms the reveal allowance is written half and half to the two rooms.
  • Tile zone: if the wall type has a lower zone, the part from the floor up to the tile height is the lower zone and the rest is the upper zone; the opening and reveal allowance is written to the zone it falls in.
  • Skirting = wall and parapet length − width of the openings that touch the floor (doors).
  • Skirting parts: an inner corner is a corner where two walls meet as seen from inside the room; an outer corner is a corner where the wall corner projects into the room (in an L-shaped room 5 inner, 1 outer corner); an end is every end where the skirting is cut (the two sides of a door, the ends of an open edge). A corner that continues straight is not counted.
  • An edge or part of an edge with no wall panel in front of it is counted as open: it does not enter the wall area and skirting, the row turns yellow and the warning list says how many metres were counted as open. A gap shorter than 30 cm between two panels (corner) counts as wall.

How the type of a room edge affects the quantities (the type is given from the Edges section of the room properties or by right-clicking the room; see the "Rooms" topic):

  • Automatic: the part with a wall panel in front is counted as wall, the rest as open (default).
  • Wall: the whole edge is wall at full height, and there is skirting. Use it for a brick or reinforced concrete wall that is not in the model.
  • Open: there is no wall or skirting; it is not counted even if there is a panel, and its door is not deducted.
  • Railing: there is no wall or skirting; its length is written in the Railing (m) column.
  • Parapet: edge length × parapet height (1100 mm if empty) counts as wall; there is skirting.

The Finish Quantities tab gives the net quantity of each material from the assigned finish types (coat count included, waste and package excluded) and says where it is used in the Rooms column. The materials of the roof, exterior facade and ceiling insulation types are here too.

Roof and eaves quantities

The Roof and eaves tab measures every roof in the project; the model does not change. Roofs built with Create roof are recalculated with the values in their record (boundary, shape, slope, eave allowance). Roofs drawn by hand are listed as Manual roof 1, 2…. Columns:

  • Plan area (m²): the area of the roof in plan (eave and gable overhang included).
  • Sloped area (m²): the real area in the plane of the slopes; the covering, OSB and waterproofing membrane are calculated from it.
  • Eaves / gutter (m): the lower edge of the slopes; the length of the rain gutter and eave profile.
  • Gable edge (m): the sloped outer edge at the ends of a gable roof, measured along the slope.
  • Ridge (m): the top line of the two slopes; on a mono-pitch roof the upper edge is here too.
  • Hip (m) and Valley (m): the breaking lines between two slopes that go down and that go up.
  • Step / abutment (m): the step between two slopes at different levels.
  • Soffit (m²): the plan area of the roof that falls outside the wall frame; "—" if no wall is found.
  • Gable wall (m²): one face area of the gable walls (the triangular wall at the end of a gable roof).
  • Cladding counted on panels: the cladding of the roof panel or truss itself; for information (see "Double-count protection" below).

The common edge of two slopes is counted once. Joined roofs (a wing joined to the main roof, a dormer) are measured together: the part of one roof that lies under another is not counted, the overlapping area does not enter twice; the line where two roofs meet is written as valley. Openings in the roof (a roof window, the opening a dormer makes in the main roof) are deducted from the area: the real area of the opening from the sloped area, its footprint in plan from the plan area; the soffit is not affected by the opening. At the bottom the Roof faces table gives the slope, plan area and sloped area of every slope.

Assigning a roof type: from the Roof type list in the row, choose a type whose surface is Roof. The choice is saved on the roof and can be undone; it stays even if the roof is rebuilt, and a newly built roof takes the last used type. On a hand-drawn roof the choice is written to all panels or trusses of the roof. The materials of the type are multiplied by the measures of the roof and pass to Finish Quantities and the Material List; the name of the roof is written in the Rooms column. A roof with no type assigned appears in the warning list.

Hand-drawn roofs:

  • Roof panels that touch each other are one roof. The measure is taken from the panels' own boundary; openings in the panel (roof windows) are deducted. A panel steeper than 78° is counted as a wall and is not included.
  • If there is no roof panel, the surface is built from the top line of the trusses. The gable overhang beyond the end truss is not counted because it is not in the model; where there is no truss at the corner of a hip end, the small triangles at the corner are missing.

To build a roof see the "Create Roof, Truss, Dormer and Railing" topic.

Exterior facade quantities

The Exterior facade tab measures the exterior facade of the building from the model at every opening; the model does not change. The outer face (cladding included) of the wall panels sitting on the building perimeter of each level is counted with the outside measure: the end of the opposite wall at the corner and the floor edge between levels are included; gable and parapet panels are also added to the facade they are on. Rows are divided by direction according to the outward-facing face (north is +Y, the same as the elevation views):

  • Length (m), Gross area (m²), Openings (m²) and Net area (m²). Net area = gross − openings; the layers of the facade type are multiplied by it.
  • Door and Window: count.
  • Base (m): the bottom edge of the facade on the lowest level; doors that open from the ground are deducted.
  • Window sill (m) is the sum of window widths, Reveal (m) is the two sides + top of doors and windows, Head (m) is the sum of door and window widths.

At the bottom the net facade area and the number and length of outside corners are written. Only corners that project outward are counted; steps shorter than the wall thickness are not counted as corners.

Facade type: choose a type from the Facade type list at the top of the tab. The choice is saved in the project, can be undone and applies to the whole exterior facade of the building. If no type is chosen, no facade material is counted and no warning appears (this is normal for panels whose facade is finished in the factory).

Ceiling insulation quantities

The Ceiling insulation tab measures the ceiling of every room; the insulation is above the ceiling. The part of the room ceiling that has another level above it is counted as between floors, and the rest as under roof; under a set-back upper floor the ceiling is split in two.

  • Columns: Ceiling area (m²), Under roof (m²), Between floors (m²) and Status (Automatic, Outside the building: not insulated, Manual: yes, Manual: no).
  • In automatic mode, the part of the room that is inside the building perimeter of the level is insulated. A room with more than half outside the building (veranda, porch) is not insulated.
  • The Ceiling insulation line in the room properties can be Automatic, Yes (whole ceiling) or No.
  • At the top of the tab, choose separate types for the Under-roof ceiling and the Between-floors ceiling (for example 2 × 5 cm glass wool under the roof, 5 cm rock wool between floors). The choice is saved in the project and can be undone; if no type is chosen, no insulation material is counted.
  • Double-clicking a row selects the room in the model.

Double-count protection

If a material is both in the cladding of a panel and in a finish type (exterior facade, roof, ceiling insulation, room wall or ceiling), the program counts it once, on the panel: the same layer in the finish type is deducted from the quantity by the amount the panels cover that face. This deduction is reflected in the Material List and the quote. The warning section of the Quantities window opens automatically in this case and the double-count warnings appear at the top of the list.

  • Which face: on the facade the outward-facing face of the wall panel, in a room wall the face towards the room, in a room ceiling the lower face of the ceiling, floor or roof panel, on the roof the upper face of the roof panel. If the panels cover only part of the face, only that share is deducted.
  • Same material: the program does not guess from name similarity. If the code of the quantity card equals the Product code of the cladding material, the name of the layer or the board code in the Material List (for example "Alçıpan 12,5 1200×2500"), or if the name of the card equals the name of the layer, the two count as the same; upper/lower case, Turkish letters and spaces do not matter. The most reliable way is to type the code of the quantity card in the Product code of the cladding material (see the "Material and Section Library" topic).
  • "Check" warning: if panels cover a face that has a finish type assigned but no material in the type matches this cladding, the quantity does not change and a single warning appears per type. If it is really an additional job such as paint on a wall, ignore the warning.
  • The part materials of the type (corner, sill, reveal, soffit, downpipe…) are not deducted.

Door/Window Schedule

QUANTITIES › Lists › Door/Window Schedule gives all doors and windows in the project by type with their counts and the panels they are on; untyped ones are collected by kind and size. A yellow row shows an untyped opening, a type that is not in the library or an opening that differs from the type size by more than 5 mm. At the bottom the number of doors, windows and untyped ones is written.

Net Quantities

The Net Quantities tab shows what the project contains: the net quantity of each material, without waste, packaging or price. The quantity to buy is on the Purchasing tab. The Weight (kg), Area (m²), Length (m) and Pieces columns show every measure the row has, regardless of the unit of the card; a unit that cannot be measured stays empty. For trims, corner sheets and casings, the area is the flat width of the sheet × length and the weight is area × thickness × 7850 kg/m³. For sheet strips the area is width × length. Sheet parts built by hand, bent plates, solids turned into a plate or sheet by Recognize Parts and parts that came from IFC as plates also go into the sheet row, one row per thickness, flat and bent sheets separately; the weight is flat area × thickness × 7850 kg/m³. Joint column, stair and roof trim parts are counted in their own rows, so they are not counted here a second time.

  • Lines are grouped by the Group of the material card (such as "Steel section", "Cladding board", "Consumable"). The group header shows subtotals per unit, e.g. "Steel section — 1,250.00 kg · 48.00 m".
  • Columns: Type (the card's type), Code, Material, Net, Quantity unit, Source, Warning and Rooms.
  • Materials whose card has no group are under Cards without a group, those without a card under Materials without a card, at the end. Link a material without a card to a SAP card with Link in Library… on the Purchasing tab.
  • If the project has more than one level, the Level box at the top narrows the list to one level: All is the project total; after the levels come Roof for roof material and No level for items whose level is not known (a column, stair or profile not assigned to a level, the exterior facade). What is counted from a panel is on the panel's level, room finishes are on the room's level. There is no breakdown by panel. With a level selected, Export to Excel / CSV writes that level; the list ends with a Level column.
  • Export to Excel / CSV writes the list; under each group there is a Subtotal row per unit.

Purchasing: waste and rounding to packages

The Purchasing tab is the single purchase list of the project: all materials in one table. If the same material card comes from several places, the need is added up and rounded to a package once (12 m + 12 m need and a 20 m roll → 24 m → 2 rolls). Because the board layout is a heavy calculation, the list is calculated only when this tab is opened and on Refresh.

  • Source: the places the row comes from (such as "Room finish + Steel section").
  • Net: the sum of the sources, in the quantity unit of the card (coat count included for surfaces, pieces for doors/windows).
  • Waste % and Required: net × (1 + waste) × consumption rate, in the purchase unit.
  • To order: required ÷ package size, rounded up (half a bucket is not bought); for a material without a package it is the required amount.
  • Delivered to: the delivery place on the material card (Factory or Site); empty on a row without a card. It is also written to the CSV.
  • Warning: for example "No card" or "Card unit does not match".
  • Rooms: the rooms where the finish material is used.
  • The Level box (with more than one level) narrows the list to one level. With Order level by level off, the project is ordered once: packages and boards are rounded on the project total, and a level's To order quantity and amount are its share of the total (half of 3 buckets is 1.50 buckets). With it on, every level is a separate order: packages are rounded per level and boards are nested per level; All and new quotes take the sum of the levels (2 + 2 = 4 buckets in the same example). The setting is saved with the project and can be undone.

The sources of the rows:

  • Room finish: finish types (roof, exterior facade and ceiling insulation included); the code is the code of the material card.
  • Door/window: the material card of door/window types; pieces.
  • Steel section: the profiles in the panel frames, by section name (for example C90x40x1.2); the length is the machine cut length of the profile (the assembly gap of the active machine is subtracted, the same as the sheet and the work order). For cold-formed sections it is measured in kg, for others in m; pieces are counted too. If a SAP coil code is entered for the section, that section is counted by coil code and in kilograms; sections that use the same coil are a single row (see the "Material and Section Library" topic).
  • Frame fastener: screws, rivets or bolts in the frame connections (the same as the frame screw count in the production work order); the code is like KARKAS-VIDA-4.8; pieces.
  • Cladding board: the new full boards in the project-wide board layout (those coming from offcuts are not counted), by material and size (like "Alçıpan 12,5 1200×2500"); pieces and m². Cladding layers that are not cut (rock wool, barrier, profile tape) and the trapezoid door/window closures are in this source too.
  • Consumable: the cladding consumable calculation (screws, tape…); the code is the product code, or the product name if there is none.
  • Roof covering and trims: the covering sheets built with Create roof, one row per material and length (like "Trapez 0.50 L=5050"), in pieces. If there is no card for that length, the row is measured and priced with the card of the material. Gable and eave trims and corner caps come in one row per material and thickness (like "Boyalı sac RAL 7016 1 mm"), in kilograms. A trim with no material chosen keeps the name of the part ("Saçak kapatması 1 mm"). If the chosen material has no card, the row is priced with the old card of the part and shows the warning Priced with the old card, create its own card.
  • Foundation anchor and Sill sealer: the anchor, washer and bottom flange tape in the foundation connection setting of the panel.

Using the list:

  • The Source filter above the table filters the table and the CSV to a single source; for example you can give a painting subcontractor only the Room finish rows. The package calculation is not affected by the filter.
  • For a row to be priced, there must be a card with that code in the library. Add Missing Cards adds cards without prices to the library for steel, board and consumable rows that have no card (it first shows the cards to be added and asks); enter their prices afterwards in QUOTES › Prices › Price List. You define room finish and door/window cards yourself.
  • Link in Library… ties the selected row to a card that is already in the library, for example a card that came from the SAP list; so you do not need to open a second card for the same material. Select the row, press the button and choose the card in the material picker that opens. In the picker the Matching unit option shows the cards in the unit the row can be measured in; a row is not linked to a card in another unit, and the program says why.
  • The link is stored in the Quantity Library and applies to all projects: from then on that code is counted under the code of the chosen card in the list of every project. Rows linked to the same card are summed in a single row.
  • A row whose card was opened by hand (not from SAP) can also be linked. After the link, if that manual card is not used anywhere in the library, the program offers to delete it; a card used in a finish type or door/window type, or one with a price, is not offered.
  • On a steel profile row (for example C90x40x10x1.2) the link is made not to a card but to the coil of the section: the picker shows the coil cards, and the chosen coil is written to the same place as Pick coil… in the sections. From then on the profile is counted in kg from that coil. A section whose weight is unknown cannot be linked to a coil.
  • A row whose card already came from SAP and a row that comes through a link are not linked again. You see and delete the links on the Links tab of the QUANTITIES › Materials › Material Cards window; the row of a deleted link is counted under its own code again.
  • You can change the quantity unit of a card: a steel card can be kg, m or pieces, a board card pieces or m². If the unit of the card cannot be measured on that material (for example an m² card on a steel profile), the row says "Card unit does not match" and is not priced.

Export to Excel and CSV

  • Every tab of the Quantities window has an Export to Excel / CSV button, and the Model Quantities window has Export Excel / CSV.... Model Quantities, the rebar and mesh lists, the joint check report, the internal cost breakdown of the quote, the price list and the shipping list are saved the same way.
  • The save window first offers the format chosen in ⚙ Settings › General Settings › General › List files; the initial setting is Excel (.xlsx). In the Excel file the columns are as wide as their content, the header row is bold and stays visible when you scroll down; the numbers are real numbers, Excel shows them in your own language and you can sum them.
  • You can still choose the other file type in the save window. In the CSV the numbers use a point (for example 2.83); Excel in a language with a decimal comma, such as Turkish, may take such a number for a date ("Şub.83") when the file is opened by double-click. Save a list you will use in Excel as an Excel file.
  • The file of the Material List follows the Source filter, and the file of Model Quantities follows the selected Category. The Roof and eaves CSV writes the roofs and slopes together, and the Exterior facade CSV writes the direction rows, the total and the outside corners together.
  • CSV headers are written in the output language (see the "General Settings" topic).