31
Quotes
The QUOTES tab holds material prices and prepares a customer quote from the Material List of the project. QUOTES is a separate package module; price and cost information is visible only in the windows opened from this tab.
Step by step
- Enter the prices of the material cards with QUOTES › Prices › Price List, or take them from Excel with Import Prices.
- Click QUOTES › Quote › New Quote: a new quote (T1, T2…) is built from that day's Material List.
- Enter the client, currency, rates, VAT, overhead and profit percentages; add extra lines if needed and click Save.
- Get the document to give to the customer with Customer Quote (PDF).
Price list
QUOTES › Prices › Price List opens the Quantity Library window on the Price List tab; this tab is visible only when opened from QUOTES. Every material card has a row:
- Package price and Currency (TRY, USD, EUR, GBP): the price of one package; for a material without a package, the price of one purchase unit.
- Labour unit price and Labour currency: the labour of one quantity unit (the unit is written in the Unit column). If left empty, labour is not calculated.
- VAT %: the VAT rate of the material in quotes. If empty, the quote's default rate is used. Changing the rate does not change the update date of the price.
- Supplier and Updated: the date of a row whose price you change becomes today.
- Status: a row without a price says "No price"; a price older than 30 days or without a date says "Old price"; a row with an old price is yellow.
- The Search box above filters as in Material Cards. Changes become permanent with Save.
Updating prices with Excel
- On the Price List tab, take the file with Export (in the list file format of General Settings; Excel at first).
- Change the prices in Excel and save the file; it can stay Excel or CSV.
- Click Import (or QUOTES › Prices › Import Prices on the ribbon) and choose the file; Excel and CSV files are read. Rows are matched by code; codes that are not in the library are skipped and listed with their row number.
- Click Save; only then do the changes become permanent.
- Both the Turkish Excel format ("2.450", "2.450,50") and dotted decimals ("2450.50") are read in numbers.
- The date can be yyyy-mm-dd or dd.mm.yyyy; if the date column is empty, the day of import is written. The currency has three letters (TRY, USD, EUR).
m² prices
A preliminary quote given without a model is calculated with m² prices. These prices are on the m² Prices tab of the Price List window; this tab too is visible only when opened from QUOTES.
- Add Price adds a new row, Copy copies the selected row, Delete Selected deletes after asking. Quotes already given are not affected by a deleted price.
- Kind: Building type (such as housing, warehouse, office; multiplied by the floor area), Exterior wall, Interior wall, Floor or Roof (multiplied by their own areas). You can open building types with any name and in any number.
- Price per m² is the cost: material and labour. Overhead, profit and VAT are added in the quote. The Updated date of a row whose price changes becomes today; a row with a price older than 30 days is yellow.
- Suggest from Open Project suggests an m² price for the selected building-type row from the open project: the cost of the quote that New Quote would build at that day's prices (without overhead, profit and VAT) is divided by the gross floor area. The gross area is the area of the outer wall outline of every level. The program shows the result and asks; if you confirm, the price and the Source (sample project and day) are written to the row.
- Materials without a price do not enter the suggestion and are counted in a warning; the suggestion is then too low. If a currency has no exchange rate, no suggestion is made.
- Changes become permanent with Save.
Creating a quote
QUOTES › Quote › New Quote builds a new quote from the current Material List and opens the Quotes tab of the Quantities and Quotes window. QUOTES › Quote › Quotes opens the same tab with the saved quotes; + New Quote in the tab also builds a new quote.
- Every material with a price is a row; for a material with a labour price a labour row is added too. A material without a price or a card does not enter the quote and is reported by name.
- A material row is priced with the To order quantity of the Purchasing tab, that is the package quantity: waste, leftover board from cutting and paint left in the bucket are included in the quote price. The labour row is calculated from the net quantity. With Order level by level on, the material quantity is the sum of the levels' separately rounded orders.
- Prices and rates freeze: the quote copies the prices of the day it was created. Even if the price list changes later, a quote already given does not change. To calculate with current prices, create a new quote; rates and percentages come from the previous quote.
- The Client box is filled with the client in the project information; you can change it.
Preliminary quote
QUOTES › Quote › Preliminary Quote prepares a quote from m² prices without a model. The window has two ways:
- Quick: choose a Building type and type the Floor area (gross, m²). If the open project has a level outline, Take from open project fills in the area.
- Detailed: type the exterior wall, interior wall, floor and roof areas in the Surfaces table and the counts of the types in the Doors and windows table. A door or window is priced with the price of its type's material card in the Price List.
- m² Prices… opens the Price List on the m² Prices tab; after saving, the window takes the new prices and keeps what you typed.
- Create Quote builds the quote and opens it on the Quotes tab. A preliminary quote gets its own number (T1, T2…), is marked "preliminary" in the list, and the title of the customer document is PRELIMINARY QUOTATION.
- Overhead, profit, VAT, rates and extra lines are edited as in a normal quote; prices freeze. Items without a price do not enter the quote and are reported by name.
- When the model is built, New Quote builds the detailed quote with its own number; the preliminary quote stays in the list.
Editing a quote
Choose the quote from the list on the left; on the right the header information and the rows are shown.
- Currency: the currency of the quote (for example TRY). If there is another currency in the rows, its box opens in the Rates line. The rate is always entered as the equivalent of one unit of the foreign currency: for a euro row in a TL quote "1 EUR = 48.05 TRY", for TL rows in a dollar quote "1 USD = 41.5 TRY". A currency with no rate entered does not enter the total and no quote document is produced.
- VAT %: the rate for materials with no VAT in the Price List, and for labour (20% on the first quote). A material with a VAT in the Price List uses its own rate. In the total every rate is a separate line (for example VAT 10%, VAT 20%).
- Overhead % and Profit %: added to the cost of rows with Markup ticked. Overhead = cost × overhead %; profit = (cost + overhead) × profit %. VAT is calculated from the amount with profit.
- Spread overhead and profit into prices on the customer quote: if ticked, unit prices in the customer PDF grow proportionally and the profit line is not visible; if not ticked, overhead and profit are separate lines. The total is exactly the same to the cent in both cases.
- + Extra Line adds a free item such as transport, scaffolding or assembly; every field of an extra line can be edited and it belongs only to this quote. Delete Line deletes only extra lines.
- In material and labour rows only VAT % and Markup change; these rows come from the Material List.
- What you write in the notes box (payment and delivery terms, validity period…) is written at the bottom of the customer PDF.
- The summary at the bottom refreshes instantly: materials, labour and extras, the cost total, overhead and profit, net total, the VAT lines and the grand total.
- Save saves the changes. If you switch to another quote or close the window while there are unsaved changes, the program asks. Delete Quote deletes after asking. Creating, saving and deleting a quote are undone with Ctrl+Z.
Quote documents
- Customer Quote (PDF): the quote to give to the customer.
- Internal Cost Breakdown (PDF): the in-house breakdown: original unit price and currency, rate, cost, net margin, overhead and profit rate.
- Internal Breakdown (Excel / CSV): the same breakdown, for working in Excel.
- PDFs open first as a preview; saving is optional. Unsaved changes are saved before a document is produced. Documents are written in the output language.
Where quotes are stored
- Quotes are not written into the project file (
.axi). When the project is saved, they are saved in protected form into the quote folder on your computer, and they come back when the project is opened. This way, when you send the project file to a customer or another office, your prices and quotes do not go with it. - To move quotes to another computer, use ⚙ Settings › General › Back up…; the quote folder is included in the backup.